Work completed this week:

  • Approximately 250 feet of 48-inch sanitary sewer installed and air tested.
  • Manhole #6 installed.

 

Summary of activities expected for next week (August 17 – 22):

  • Continue 48-inch sanitary sewer installation.

 

Installing 48-inch sanitary sewer