Underground utility work has continued this week, with sanitary lateral installations on Dryden. Additionally, road rebuilding continues on Dryden and Wood. Next week underground utility work will continue on Wood, moving towards Union.
Work Completed this Week
- Sanitary lateral installation on Dryden from Wood to Jefferson.
- Road rebuilding on Wood street and Dryden street from Wigton to Jefferson.
Anticipated Work Next Week
- Continuing sanitary sewer installation on Wood west of Hart towards Union
- Road rebuilding will continue on Wood and Dryden.
Please Note: Undergrond utility work continues on Wood street. Dave’s party store is accessible on Hart Street from the north.