Progress Report:

McCormick Sand continued water main installation on Ferry Street south to north of Robbins Road. Asphalt surface road restoration on Ferry Street was completed between Taylor Avenue and Grant Avenue. The Contractor is replacing sanitary sewer laterals and storm sewer catch basin leads from Robbins Road to Orchard Avenue which were disturbed during water main construction.

Upcoming Work:

McCormick Sand will close 172nd Avenue south of Robbins Road starting on Monday, August 19. Contractor will start removing pavement to prepare for water main installation on 172nd Avenue south of Robbins Road. Robbins Road will be closed starting Wednesday, August 21 and McCormick Sand will begin proceeding with water main installation to the south.