This Week:
  • Fer-Pal completed all of the lining installation along 4 Mile Road and West River Drive, south of the railroad tracks.
  • Fer-Pal also started lining some of the water main along West River Drive between the railroad tracks and Leland Avenue.
  • Fer-Pal continued pressure testing and reinstating water service connections on sections that were lined this week.
  • Hoffman Brothers was back on-site end of this week to begin connecting the lined water main along 4 Mile Road to the existing water main.
Next Week:
  • Fer-Pal will line the water main between Leeland Avenue and Lamoreaux Drive. This work is planned to take place over night to limit the traffic impacts. Water main lining work should be completed after next week.
  • Hoffman Brothers will continue to install new ductile iron water main in the lining pits to reconnect the lined water main sections. New valve and new hydrants will be installed in select locations.
  • Restoration work at pit locations may start next week depending on weather and progress.