This Week:
- Milbocker completed water service replacements along Miramar between Eldon and Airway.
- Milbocker’s second crew began installing water main along Miramar from the Eldon intersection working south to Northgate.
- Milbocker is scheduled to complete water main connections to the existing water mains at the north and south Daylor intersections today, weather dependent. If these connections don’t take place today they will be rescheduled for next week.
- Milbocker completed lawn restoration work along Eldon. New lawn care guides were distributed to residents this week. Please make sure to follow these guidelines to ensure that your new grass comes in nicely.
- Milbocker began grading out for sidewalk replacement along Miramar.
Next Week:
- Concrete crews will be on site Monday to begin replacing sidewalk and curb and gutter along Miramar between Eldon and Airway.
- Milbocker will continue installing water main along Miramar and should get to Plainfield Ave by the end of the week.
- Milbocker will complete the water main connections at the two Audley intersections. Residents affected by this temporary water shutdown will be notified by the Plainfield Water Department prior to the planned shutdown.
- After all of the water main connections at side streets have completed, Milbocker will complete the connection to the existing water main on the north side of Airway. Airway will be closed to thru traffic and a detour route will be posted.