Maple Street: Concrete curb, ADA ramp and driveway work has been completed. Unfortunately, a portion of the newly constructed sidewalk at the intersection of Maple and Fremont Street was installed at an incorrect depth. This will be corrected during sidewalk installation along Lincoln Street. Maple Street base paving was completed Tuesday of this week. Landscaping Restoration is underway and is planned to continue into next week.
Lincoln Street: The water main tie-in at Lincoln and Maple Street was completed Wednesday of this week. This was the last tie-in for the project and marks a milestone toward completion of the water main work. Storm sewer construction is planned to be completed by the end of the week. Following storm sewer construction, road grading will commence to prepare for school beginning next week. The base course paving will still not be in place, so drivers should expect a bump in the road at the project limits. Curb installation is planned to begin Tuesday of next week.