This Week:

  • Dean’s began transmission main installation across from the Pump Station driveway and is working west along Buth Drive.
  • Select tree clearing was completed on Buth Drive to facilitate the water main construction.

Next Week:

  • Dean’s will continue transmission main installation west down Buth Drive to Pine Island Drive.
Please contact any project representative if you have questions or concerns.