This Week:
  • K&R continued work on storm sewer replacement in Northville Drive between Lakehurst and Leelanau.
  • K&R completed water main installation on Northville Drive between Leelanau and Nippon.
  • Northville and Leelanau were closed to thru traffic.

 

Next Week:
Northville (Leelanau to 5 Mile)
  • K&R will complete water main installation to Manitou and test this section so that water services can be installed.
  • K&R will begin sanitary sewer replacement.

 

Northville (Lakehurst to Leelanau)
  • K&R will begin road and sidewalk reconstruction.
  • K&R will complete storm sewer replacement.

 

Leelanau
  • K&R will begin road and sidewalk reconstruction.
  • K&R will complete storm sewer installation between Northville & Keeweenaw.

 

Northville and Leelanau will continue to be closed to thru traffic.

Please contact any project representative if you have questions or concerns.