All water services are ready for connection. If you have not already coordinated with a general contractor to get your free water service installed, you must do so as soon as possible to ensure you can meet the sixty (60) day connection requirement. If you have any questions about the process, please call Jeremy Kamp at (616) 432-6709.

This Week:

  • Schippers worked on restoration along 10 Mile Road and final project cleanup throughout the site.

Remaining Work:

  • A date for final paving of Brent Drive and the road patches along 10 Mile has not been set yet. Schippers is working with Superior Asphalt to schedule this as soon as possible.
Please contact any project representative if you have questions or concerns.