Base course paving is underway on Campbell. Top course (final) paving on all of Campbell is scheduled for Monday, August 5. Water service work on Dartmouth will continue the week of August 5-9. Water main installation/testing should be completed on Commonwealth next week. Water service work on Commonweatlh should begin the week of August 12.

There are a few soft soil issues on Pinehurst south of Kenwood that need to be addressed before final top course paving can be completed. We will post a schedule on that work as soon as it is available.