Progress Report:

This week Milbocker completed water main installation along Miramar up to Airway. The majority of the concrete restoration was completed along Eldon. Milbocker also started on water service replacements on Miramar between Eldon and Daylor.

Upcoming Work:

Next week Milbocker will continue to replace water services along Mirmar, north of Eldon. Lawn restoration work along Eldon will continue next week. Milbocker will work with the Plainfield Water Department to test the new water main between Daylor and Airway. Some storm sewer work at the intersection of Miramar and north Daylor may take place towards the end of next week. This intersection will be closed for a day to facilitate the storm sewer work. Depending on how the water service replacement work goes, Milbocker may start installing water main along Miramar, starting at Eldon and working south to Plainfield.