This week Dean’s and De Witt completed:

  • Force main installation through the Saddle Ridge neighborhood. The majority of the construction work within the development is now complete. Dean’s will work on testing the new force main pipe and restoration of disturbed areas over the next few weeks.
  • Force main installation under US-131 between Edgerton and Elstner.
  • Installation of the 10-foot diameter wet well structure, meter chamber, and valve chamber at the lift station site.
  • Installation of some of the gravity sanitary sewer that will eventually connect the existing Saddle Ridge wastewater collection system to the new lift station wet well.

Next week Dean’s and De Witt plan to:

  • Complete force main installation along Edgerton.
  • Complete force main installation at the lift station site.
  • Begin construction of the gravity sanitary sewer and force main discharge manhole near 10 Mile Road and Wolven Avenue.
  • Begin horizontal directional drill work along Wolven Avenue, starting at 10 Mile Road and working north.
  • Begin restoration work within the Saddle Ridge neighborhood.