Progress Report

The west and south half of Wildwood Creek will be pulverized on Saturday (8/21) in preparation for water main construction to start middle of next week.

This week:
  • Wyoming completed water main installation along Belmont Avenue and began the testing process of this new water main.
  • Wyoming installed water main across Van Dam Drive at Pixley Avenue.
  • Wyoming began water main installation along the north side of Van Dam Drive heading east to Wildwood Creek Drive.
Next week:
  • Wyoming will complete water main installation along Van Dam Drive.
  • Wyoming will begin water main installation on Wildwood Creek Drive. Wyoming plans to start water main construction at the dead end and work their way out to Van Dam Drive. Access during construction will be maintained, however, we ask that you have patience with the crews as there may be some minor delays. Please plan accordingly, Wyoming will be working to install the water main as quickly as possible.

Once the water service stub has been installed out to the public road right-of-way in front of your house, you will receive a letter from our staff on site informing you that your water service is ready for connection. You will have sixty (60) days from the date of the letter to connect to the municipal water system. If you have not already contacted a private water service contractor about installing your free water service, you should do so as soon as possible to ensure you can meet the sixty (60) day connection requirement.

 

What to Expect

August
  • Water main construction along Van Dam Drive.
  • Water service construction along Belmont Avenue.
  • Water main construction along Wildwood Creek Drive.
Long Term
  • As soon as the water main in one area is complete, tested, and ready for water service connections, Plainfield Township will communicate with you to start the process of installing water services on private property.
  • Estimated project completion date: October 9

 

Project Timeline

  • August
    • Water service construction on Belmont Avenue
  • August – Mid-September
    • Water main and water service construction on Van Dam Drive
  • Late-August – September
    • Water main and water service construction on Wildwood Creek Drive
  • Mid-September – Mid-October
    • Water main and water service construction on Pixley Avenue