Progress Report

This week:
  • Dean’s continued 12-inch water main installation along Packer Drive up to around Rogue Hollow Court.
  • Dean’s completed water service installations between Las Vegas Drive and Rogue Hill Court. This completes the work in the area along the Rouge River where ground water dewatering is necessary. The dewatering system will be removed next week.
Next week:
  • Dean’s will continue to install 12-inch water main along Packer Drive.

Once the water service stub has been installed out to the public road right-of-way in front of your house, you will receive a letter from our staff on site informing you that your water service is ready for connection. You will have sixty (60) days from the date of the letter to connect to the municipal water system. If you have not already contacted a private water service contractor about installing your free water service, you should do so as soon as possible to ensure you can meet the sixty (60) day connection requirement.

Only those houses along Packer Drive (including the two gravel drive easements south of Rogue Hill Court) and Van Dam Drive will receive a water service as part of the 2021 construction and will be required to connect to it this year. Water main and services on Rogue Hill Court, Rogue Hollow Court, and Packer Woods Drive will be constructed next year with connection required for these houses in the spring of 2022.

 

What to Expect

August
  • Water main and water service construction on Packer Drive up to the White Pine Trail.
September
  • Rogue River crossing
  • White Pine Trail crossing
Long Term
  • Water main and water services along Packer Drive and Van Dam Drive will be installed in 2021. Water main and water services along northern side streets and private drives off of Packer Drive will be installed in the spring of 2022.

 

Project Timeline

  • August
    • Water main construction along Packer Drive up to White Pine Trail and southern most private drive easement
  • Labor Day Weekend
    • Water main construction crossing the Rogue River
  • September
    • Water main construction crossing the White Pine Trail and water service installation along Packer Drive
  • Late September – Mid-October
    • Water main construction and water service installation along Van Dam Drive
  • October
    • Packer Drive road reconstruction
  • Late October
    • Water main construction along private drive easement just south of Rogue Hill Court
  • April 2022
    • Water main construction along Packer Woods Drive
  • May 2022
    • Water main construction along Rogue Hollow Drive and Rogue Hill Drive