Progress Report

This week:
  • Schippers concrete subcontractor, M&S Construction, completed the concrete curb construction
  • Schippers finished road grading on Bonneville Drive, north of Brisam Street, and court streets in preparation for paving next week.
  • Schippers prepped the parking lot at 5 Mile Road and Plainfield Avenue in preparation for paving next week.
Next week:
  • Base course paving is scheduled for Monday (8/23) north of Brisam Street. Please plan accordingly as access will be intermittent until the paving is completed.
  • Schippers will work on adjusting manhole and catch basin covers in preparation for final top course paving in September.
  • Schippers landscaping subcontractor, H&K Landscaping, will be on site over the course of the next few weeks to spray all the weeds in the topsoil with a weed killer. Once the weeds have had a few weeks to die off, they will be back to finish spreading topsoil and complete the final lawn restoration in the beginning of September.

 

What to Expect

August
  • Road reconstruction north of Brisam Street
  • Parking Lot restoration at 5 Mile Road and Plainfield Avenue
  • Water Service conversions along Plainfield Avenue
September
  • Water Service conversions along Plainfield Avenue
  • Final paving, restoration, and project clean up

 

Project Timeline

  • August
    • Road reconstruction
  • August – September
    • Plainfield Avenue water services
  • September
    • Final paving, lawn restoration, and project cleanup
Grading of the aggregate base in preparation for paving next week