The first phase of the road improvements was started this week; contractor milled off the old asphalt in about half of the neighborhood in preparation for paving.

As of August 20, sixty-one (61) houses – 86% of the neighborhood – have connected to the municipal water system.

Quotation forms have been received for 67 houses (94% of the neighborhood). If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so immediately. The 60-day requirement for getting water services connected has expired.

 

What to Expect Next Week (August 24 – 29)

 

Projected Timeline