Work Completed This Week

  • All underground work has been completed with the exception of a sanitary sewer tie-in at the intersection of Peck Street and Strong Avenue.
  • Jackson-Merkey Contractors, Inc. graded the existing sand subbase on Strong Avenue from Jefferson Street to east of Sanford Street.
  • Jackson- Merkey Contractors, Inc. placed and shaped the aggregate base course on Strong Avenue from Jefferson Street to east of Sanford Street.
  • Martin J Concrete, Inc. began constructing the concrete curb and gutter on Third Street, Jefferson Street and Strong Avenue through Sanford Street using a slipform curb machine.
  • Jackson-Merkey Contractors, Inc. began fine grading the aggregate base on Jefferson Street, Strong Avenue and Third Street in areas where the curb and gutter has been completed.
 

Anticipated Work Next Week

  • Martin J Concrete, Inc. is scheduled to complete the curb and gutter, driveways, sidewalks and ADA ramps for Third Street, Jefferson Street and Strong Avenue through Sanford Street on Monday and Tuesday.
  • Jackson-Merkey Contractors, Inc. will fine grade the aggregate base course on Third Street, Jefferson Street and Strong Avenue through Sanford Street.
  • Asphalt Paving, Inc. is scheduled to pave the Hot Mix Asphalt leveling course on Third Street, Jefferson Street and Strong Avenue through Sanford Street.
 

Current Road Closures

  • Strong Avenue from Fourth Street to Sanford Street.
  • Jefferson Street from Campus Street to Monroe Avenue.
  • Sanford Street at Strong Avenue.
  • Posted detour routes are in place.
Mainline curb and gutter has been reinstalled on Jefferson Street.