Progress Report

As of August 25, seventy-seven (77) houses – 78% of the project – have connected to the municipal water system.

Quotation forms have been received for 98 houses (99% of the project). If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so as soon as possible.

Dykema Excavators is working diligently to wrap up any loose ends throughout the project. Please let us know if you have any concerns.

 

What to Expect

September
  • Final punch list completion.
  • Private water service installation.