  • CL Trucking completed water main installation along Meek Drive between Herrington Avenue and Terrie Lynn Drive.
  • CL Trucking completed water service installation along Sprucewood Drive and Sprucewood Court and completed water service installation along Pine Hill Drive.
 
Next week:
  • CL Trucking will continue water service installation on Belmont Avenue and Frond Street.
  • CL Trucking will continue water main installation in Meek Drive and Korben Woods Court.
  • CL Trucking will begin testing the newly installed water main in the Hamilton Woods neighborhood.

 

Please contact any project representative if you have questions or concerns.

 

What to Expect

September
  • Water service construction
  • Water main construction on Meek Drive, south of Terrie Lynn, and Korben Woods Cour
October
  • Road, driveway, and lawn restoration

 

Project Timeline

  • September
    • Water Main Construction on Terrie Lynn Drive, Meek Drive, and Korben Woods Court
    • Water Service installation
 
  • October
    • Road Reconstruction, Driveway Reconstruction, and Lawn Restoration