Progress Report: This week, Kalin Construction continued to construct the subgrade for the pathway between the two boardwalk sections. They also installed two culverts. Their Subcontractor Riverworks Construction, continued to drive piles and began framing for the tall boardwalk. They completed the main construction of the first at grade boardwalk in just 10 days!

Upcoming Work: Next week, the crews will continue framing and construction on the taller boardwalk while working on the approach structures to the at grade boardwalk. Kalin Construction plan to begin construction on the small block retaining wall.

Extra Notes: Site safety is very important to us. Please be mindful of your travel speed in and around all construction sites.