Underground utility work has continued this week, completing sanitary sewer main and continuing storm sewer main on Wood Street.  Sanitary laterals and storm sewer will continue next week, along with additional asphalt and concrete removals in preparation for road rebuilding. 

Work Completed this Week

Anticipated Work Next Week

Please Note: Underground utility work continues on Wood street.  Dave’s party store is accessible on Hart Street from the north.