Underground utility work has continued this week, completing sanitary sewer main and continuing storm sewer main on Wood Street. Sanitary laterals and storm sewer will continue next week, along with additional asphalt and concrete removals in preparation for road rebuilding.
Work Completed this Week
- Sanitary sewer main installation on Wood from Hart to Union.
- Storm sewer installation on Wood from Hart to Union.
- Sidewalk removal on Wood and Dryden began.
Anticipated Work Next Week
- Sanitary sewer lateral installation on Wood west of Hart towards Union
- Additional sidewalk and asphalt removal on Wood and Dryden.
- Storm sewer will continue on Wood and Union.
Please Note: Underground utility work continues on Wood street. Dave’s party store is accessible on Hart Street from the north.