This Week:
- Fer-Pal has completed all of the water main lining installation along West River Drive north of the railroad tracks. Most of this work was completed at night to limit traffic impacts.
- Fer-Pal continued pressure testing and reinstating water service connections on sections that were lined this week.
- Hoffman Brothers continued connecting the lined water main along 4 Mile Road to the existing water main.
- There was one section of liner that was found to be defective in front of the American Legion along 4 Mile Road. Fer-Pal and Hoffman Brothers spent time digging additional pits this week to investigate the extent of this issue.
Next Week:
- Fer-Pal will continue to pressure test and reinstate water service connections inside the liner.
- Hoffman Brothers will continue to install new ductile iron water main in the lining pits to reconnect the lined water main sections. New valve and new hydrants will be installed in select locations.
- Fer-Pal and Hoffman Brothers will continue to investigate the section of defective liner early next week and hope to have a plan to completely address this issue by the end of next week.