This Week:
- B&L Excavation completed the tie-in to the existing water main at the intersection of Wateredge and 10 Mile.
- B&L Excavation completed water service stub installations along Wateredge.
- B&L Excavation began road grading in preparation for paving next week.
Next Week:
- B&L Excavation will complete installation of water main along Freska Pines.
- B&L Excavating will pressure test and disinfect the new water main along Freska Pines after the installation is complete prior to water service stub installation.
- Paving of Wateredge Drive is tentatively scheduled for Wednesday and Thursday next week.
Please contact any project representative if you have questions or concerns.