This Week:

  • Montgomery completed water service installation on Jewell Avenue and 11 Mile Road.
  • Montgomery began water service installation on Sag Harbor in the Cottages on the Rogue Neighborhood and is working around the loops counterclockwise.
  • Montgomery began removing excess sand from Booth Bay Circle and began placing the gravel base for the new road.
  • Jewell Avenue and 11 Mile Road were closed to thru traffic.

 

Next Week:

  • Montgomery will complete water service installation in the Cottages on the Rogue Neighborhood.
  • Montgomery will continue placing new gravel base in locations where the water main was installed under a road surface in preparation for the asphalt to be replaced later in September.
  • Jewell Avenue and 11 Mile Road will be closed to thru traffic.

 

Please contact any project representative if you have questions or concerns.