This Week:
- Dean’s continued transmission main installation west along Buth Drive and will be close to finishing the installation on Buth Drive today.
- Dean’s is currently about one week ahead of their anticipated schedule.
- Buth Drive was closed to thru traffic.
Next Week:
- Dean’s will complete transmission main installation at the intersection of Buth Drive and Pine Island Drive.
- Dean’s will cap an old water main on the west side of Pine Island Drive that is no longer in use and crosses Pine Island Dive just north of Pendleton Drive.
- Two-way traffic along Pine Island Drive will be shifted west to create a work area for transmission main installation on the east side of the road.
- Dean’s will begin transmission main installation along Pine Island Drive starting at Buth Drive and working south.
Please contact any project representative if you have questions or concerns.