Work completed/in progress from the last update:

  • Lakewood/River intersection closed and traffic shifted in River.
  • Pavement removal in Lakewood/River intersection and within River.
  • Transmission main installed part way through the Lakewood/River intersection, pipe crew is now moving south down River.
  • Continued with Holland Township 16″ water main installation. Installation complete to just east of Elm Street.
  • Road resurfacing project placed top course between 152nd and 144th.
  • HDPE drill pipe connection completed and restraint collar formed.

 

Anticipated activities for the upcoming week include:

  • Continue transmission main installation through Lakewood/River intersection.
  • Replace concrete improvements and re-build road within Lakewood/River intersection as feasible. Anticipate intersection will be re-paved the week after Labor Day.
  • Pavement removal in River.
  • Continue Holland Township 16″ water main installation.
  • Restore Park Township property.
  • Install storm sewer between Aniline and Division for road reconstruct project.
  • Install second groundwater treatment system and relocate current groundwater treatment system.