This Week:
- Milbocker completed the water main connection at Airway Street.
- Airway Street was repaved the same day of the water main connection.
- Concrete sidewalk, curb, and driveway replacements continued along Miramar Avenue north of Eldon Street.
- Milbocker worked on replacing water service lines along Miramar Avenue south of Eldon Street.
- Storm sewer at the northern Daylor intersection was completed.
Next Week:
- Milbocker will work on the water main connection at Plainfield Avenue. This is anticipated to take a few days to complete so Miramar Avenue will be close at Plainfield Avenue. Plainfield Avenue will have a single lane closure from Jupiter Avenue to Miramar Avenue.
- Any water services that were not completed this week will be finished up next week.
- Concrete work will continue on the north end of Miramar Avenue.
- There is concrete pavement under the asphalt at Plainfield Avenue and it will have to be replaced prior to paving. It is anticipated that the Miramar Avenue and Plainfield Avenue intersection will be closed for the next two weeks to facilitate this work.