This week concrete curb and gutter was poured on Airway Street, Al’s excavating also continued preparing the pathway aggregate grade, and removed several driveways in preparation for paving. They plan to pave the first of two courses of asphalt on Wednesday August 9th. Driveway access may be limited for short periods of time as they come through.
On Jericho, 28 Specialties has mostly finished the largest of the retaining walls! The contractor also had materials delivered for the culvert extension they will be beginning shortly. Next week Al’s excavating will continue to remove stumps along the pathway route and prepare for the construction of the next retaining wall.