This Week:

  • Water main pipe was delivered to the site and stored at the pump station property off Buth Drive. The goal of the project is to deliver more water to the ground storage tank seen in the background of the photo below to meet growing water demand in the northwest part of the Township. The project will also provide a second reliable water source feed for the tank and pump station on Buth Drive.

 

Next Week:

  • You can expect to see crews along Buth Drive marking the location of existing underground utilities.
  • Prein&Newhof will have survey crews on site staking the water main location.
  • Dean’s will begin to deliver equipment to the site in preparation for construction to begin on Buth Drive at the Pump Station site on Monday, August 15th.

 

Please contact any project representative if you have questions or concerns.