road map

water map


Work completed/in progress from the last update:

  • Lakewood and 144th Ave intersection paved and reopened.
  • Transmission main between 152nd and west HDD pit was disinfected and passed BacT testing.
  • Transitions milled between existing and new paved surfaces between 152nd and 144th.
  • Shoulder and topsoil restoration between 152nd and 144th.
  • Easement storm sewer installation for road reconstruct contract.

Anticipated activities for the upcoming week include:

  • Continue transmission main between Holland Charter Township maintenance building and River.
  • Pressure test and chlorinate transmission main from eastern drill pit to Holland Charter Township maintenance building.
  • Complete easement storm sewer installation for road reconstruct contract.
  • Shoulder and topsoil restoration between 152nd and 144th.
  • Dewatering setups, lateral replacement, and water service replacement, as necessary.
  • Mobilize and initiate mobile groundwater treatment system.