Progress Report

This week:
  • Dykema’s paving subcontractor, Superior Asphalt, completed the final top course paving on the Hopewell Drive and Stoneridge Drive cul-de-sacs. This work went later than anticipated and we apologize for any inconvenience this caused.
  • Paving of the remaining patches is scheduled for this Saturday (8/7) morning.
  • Dykema worked on lawn restoration along Elstner Avenue and installation of an access road south of the Elstner Avenue cul-de-sac.
  • Private water service contractors continue to install the private portion of the water service into resident’s homes.
Next week:
  • Dykema will work on final lawn restoration along 11 Mile Road and Elstner Avenue.

 

What to Expect

August
  • Final lawn restoration and project clean up for 11 Mile Road and Elstner Avenue
 

Important Information

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.