Belmont Avenue will be closed to thru traffic through next Friday (8/13.) Please follow the posted detours around the construction areas.

Packer Drive will be closed to thru traffic through the end of October.

Due to the scare availability of 8-inch ductile iron water main pipe, CL Trucking has had to switch gears a couple of times over the last week between installing new water main and installing new water services. CL Trucking plans to continue installing water main when they have pipe available. Testing and disinfection of the new water main will be completed as they are installed. Water service installation will follow passing tests when time allows. You will be given an approximate time window of when your water service will be available for connection when you receive your approved Quotation Form. However, please be aware that the time frame is only approximate and may change based on water main pipe availability.

This week:
  • CL Trucking completed water service installation along Belmont Avenue.
  • CL Trucking continued water service installation along Pine Hill Drive.
Next week:
  • CL Trucking will complete water main installation along Pine Hill Drive.
  • CL Trucking will pressure test and disinfect the newly installed water main in the easement area, Frond Street, Herrington Avenue, Belmont Avenue and Pine Hill Drive.
  • CL Trucking intends to start water main construction in the Hamilton Woods neighborhood end of next week.

 

What to Expect

August
  • Water main construction on Pine Hill Drive
  • Water main construction on Terrie Lynn Drive, Meek Drive, and Korben Woods Court
  • Water service construction
September
  • Water service construction
Long Term
  • Estimated project completion date: October 17, 2021

 

Important Information

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

 

Project Timeline

  • Early August
    • Water Main Construction on Pine Hill Drive
  • Late August
    • Water Main Construction on Terrie Lynn Drive, Meek Drive, and Korben Woods Court
  • September
    • Water service installation
  • October
    • Road reconstruction, driveway reconstruction, and lawn restoration