Five homes have now connected to the municipal water system (see project map above). Water service quotation forms have been received for 76% of the houses along House Street. If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so as soon as possible in order to meet the 60-day connection requirement.
Road Work Update:
- The road reconstruction is scheduled to start within the next week.
- Final driveway restoration will not be completed until after the base course of asphalt has been placed to ensure driveways meet the new road grades.
What to Expect Next Week (August 10 – 15)
- Water service installation on private property
- Road work on House Street starting at Pine Island Drive
Projected Timeline
- August
- Road reconstruction from Pine Island to Imperial Pine, Lawn and driveway restoration
- August–September
- Water main installations along imperial pine