The final portions of the paving will be completed today, August 7.

Dykema continues to work on restoration by fine grading ditch lines, spreading topsoil, cleaning up wash outs and preparing to do a final seeding of the lawns and roadside areas.

A total of sixteen (16) houses have now connected to the municipal water system (see project map above). Water service quotation forms have been received for about 91% of the houses along Chandler and Herrington. If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so as soon as possible. Some residents are already half-way through their 60-day time window.

 

What to Expect Next Week (August 10 – 15)

  • Final lawn restoration
  • Water service installation on private property

 

Projected Timeline

  • August
    • Final lawn restoration and private water service work