Work completed this week:

  • Approximately 1,100 feet of force main installed. Installation completed to Acorn Path.

 

Summary of activities expected for next week (August 10 – 15):

  • Continue force main installation. Installation will generally progress from south to north.
  • Force main installation between Lakeside Rd and East Rd may be completed later. Contractor intends to skip this section and continue north of East Road.