This Week:
  • Milbocker worked on water service installations along Miramar between Eldon and Airway.
  • Milbocker completed water main tie-ins to the existing water mains at Northgate (north of Eldon) and the Daylor stub (east of Miramar).
  • Milbocker continued with lawn restoration work along Eldon.
  • The old water main along Eldon was abandoned this week with flowable fill.
Next Week:
  • Milbocker should finish up water service installations along Miramar between Eldon and Airway.
  • Water main tie-ins at the Daylor and Audley intersections will be completed in the next two weeks. Milbocker will schedule these with the Plainfield Water Department and residents whose water service will be impacted will be notified ahead of the planned water main shutdown.
  • Milbocker may have a second pipe crew available and would begin installing water main along Miramar (south of Eldon) or they will complete the storm sewer work at the intersection of Miramar and north Daylor.
  • Milbocker will begin to wrap up lawn restoration work along Eldon and will be transitioning to Miramar (north of Eldon).