Filter Building:
- Building is complete.
- The interior plumbing connecting the filters to the pumping system is complete except for 2 control valve actuators (Installation August 9).
- Electrical is finishing up, doing what they can short of Consumers connection.
- Consumers Energy is currently installing the service (have been rained off this morning).
Pump Stations (Eagle and Crooked):
- Pumps and electrical control panels have been delivered. Contractor is scheduled to begin installation August 13 with about 1 week of work.
System Startup:
- System startup is tentatively scheduled the week of August 26, with approximately 1 week to complete. Once system is operable the pumps will be turned on.