Filter Building:

  1. Building is complete.
  2. The interior plumbing connecting the filters to the pumping system is complete except for 2 control valve actuators (Installation August 9).
  3. Electrical is finishing up, doing what they can short of Consumers connection.
  4. Consumers Energy is currently installing the service (have been rained off this morning).

Pump Stations (Eagle and Crooked):

  1. Pumps and electrical control panels have been delivered. Contractor is scheduled to begin installation August 13 with about 1 week of work.

System Startup:

  1. System startup is tentatively scheduled the week of August 26, with approximately 1 week to complete. Once system is operable the pumps will be turned on.