Progress Report:
This week Miller Bridge started some work on the trail again by removing curb and gutter at the Green Street and 144th Avenue intersection. In addition, they cleared topsoil and graded for a few hundred feet of the trail east of the Bayou.
On the bridge they completed the large block retaining walls at both ends, and began to set the steel pile forms in the water for the H Piles.
Upcoming Work:
Next week they anticipate continuing work on the pile forms and pouring concrete.
In addition, they hope to complete removals at 144th Avenue and replace the concrete curb as well.