Underground utility work has continued the last two weeks, with sanitary sewer installation on Dryden and storm sewer installation on Wood. Additionally, road rebuilding has begun on Dryden and Wood. Next week road rebuilding will continue on Dryden and Wood.
Work Completed this Week
- Sanitary sewer main installation on Dryden from Wood Street to Jefferson Street.
- Sanitary lateral installation on Dryden from Wood to Jefferson.
- Road rebuilding on Wood street and Dryden street south of Wood.
Anticipated Work Next Week
- Potentially continuing sanitary sewer sewer installation on Wood east of Hart.
- Sanitary sewer lateral installations will continue on Dryden.
- Road rebuilding on Dryden north of Wood and on Wood towards Hart Street.
Please Note: Undergrond utility work continues on Wood street. Dave’s party store is accessible on Hart Street from the north.