Progress Report:

Progress continues as K&R has been working to complete the connection to the wastewater treatment plant (HAWRF), near River Ave/1st Street over the last month. This included connection to two existing force mains, pipe testing, and coordination with the Township to maintain existing flows into the plant.

River Hills Drive was temporarily restored for the winter, as more work will occur next spring.

Please find the below milestone video, outlining the work completed thus far.

Upcoming Work:

K&R will proceed with force main installation along the HBPW electric corridor between Lakewood Blvd and James Street. This is expected to extend through January/February, weather dependent.