Progress Report:
This week Miller Bridge completed removing form work from the deck expansion and also completed concrete work on the bridge. The also started work on the new guardrail.
Upcoming Work:
Next week they plan to focus on cleaning up the project area and getting ready to open the bridge to two-way traffic. Sometime next week they will swap lanes and finish the guardrail on the south side. On the trail they will be finishing up the driveways and installing fence on the 128th Avenue section of the pathway.