This week underground work on Densmore was completed. The roadway has been restored for the winter. No additional work is anticipated until spring.
Work Completed This Week
- Final connections of the new water main to the system were completed at Wesley, James and Marquette.
- All remaining water services were completed.
- Gravel was placed on the roadway for the season, final aggregate surface will be placed in the Spring.
Anticipated Work
- Final road grading on Densmore and lawn restoration on Densmore and East will be completed in the Spring.
- Water main work on West and Center Streets will occur next year, start dates have not been determined yet. Notificaiton to residents will be sent out once schedules are known.