Crews have completed the 36-inch and 48-inch reaming pass. A final pass to clean the drill path is underway. The pipe pull back is planned for next Tuesday. Pipe installation on the Benton Harbor St Joseph Wastewater Treatment Plant site is scheduled to start mid-March, weather depending.