Current Status/Progress Report

Private water service installation continued throughout the project area. As of February 18, twenty-seven (27) of the thirty-seven (37) houses whose water service is available for connection from 2021 construction – 73% of the 2021 project area – have connected to the municipal water system. See status map above for reference.

Homeowners must schedule the work directly with the contactor they selected. Please contact Jeremy Kamp (contact info to the left) if you have any questions.

Dean’s in tentatively planning on starting construction on April 11 pending weather and frost laws allow for this. Water main and water services will be installed on the remaining roads as follows:

 

Please contact any project representative to the left if you have questions or concerns.

 

What to Expect

February 2022 – Spring 2022

 

April and May 2022

 

Project Timeline
 Date: February/March 2022Event: Private water service installation
Date: April 2022Event: Water main construction begins again
Date: April 2022Event: Water main construction along Packer Woods Drive
Date: May 2022Event: Water main construction along Rogue Hollow Drive and Rogue Hill Drive