Current Status/Progress Report
Private water service installation continued throughout the project area. As of February 18, twenty-seven (27) of the thirty-seven (37) houses whose water service is available for connection from 2021 construction – 73% of the 2021 project area – have connected to the municipal water system. See status map above for reference.
Homeowners must schedule the work directly with the contactor they selected. Please contact Jeremy Kamp (contact info to the left) if you have any questions.
Dean’s in tentatively planning on starting construction on April 11 pending weather and frost laws allow for this. Water main and water services will be installed on the remaining roads as follows:
- Packer Woods Drive: April – Early May
- Rogue Hollow Court: Early May
- Rogue Hill Court: Late May
Please contact any project representative to the left if you have questions or concerns.
What to Expect
February 2022 – Spring 2022
- Private water service installation
April and May 2022
- Water main and water services along Packer Woods Drive, Rogue Hill Court, and Rogue Hollow Court.
Project Timeline | |
Date: February/March 2022 | Event: Private water service installation |
Date: April 2022 | Event: Water main construction begins again |
Date: April 2022 | Event: Water main construction along Packer Woods Drive |
Date: May 2022 | Event: Water main construction along Rogue Hollow Drive and Rogue Hill Drive |