This Week
Elmer’s finished the sheet piling for three of the four bridge abutments. One is on the east side of Logan’s Landing and the other two are in Medalie Park. The fourth abutment is on the east side of the Boardman River, and Elmer’s will mobilize equipment to that location soon.
Spence Brothers also made considerable progress on boardwalk decking and setting the railings.
Next Week
Elmer’s will work on finishing welding caps on the sheet pile abutment walls.
In addition to Spence Brothers’ work on the boardwalk, the railing supplier will be on site fastening bolts, tweaking alignment, and finishing off the railing.