Heirloom made good progress on electrical and concrete work again this week.  Work for the coming week will slow down due to weather with most of the progress being completed in the building.

 

Work Completed this Week (February 1 – 5)

  • Concrete Scallops were poured along the Snyder building.
  • Electrical work was completed throughout the site.
  • Various other concrete pours were completed throughout the week.

 

Anticipated Work Next Week (Weather dependent)

  • No Concrete this week due to weather
  • Roofing may be attempted on the restroom building.
  • HVAC will be worked on in the building.