Work completed/in progress:
  • Continued force main installation along Railroad corridor on north side of Continental property progressing toward 68th Avenue.
  • Flowable filled casings beneath the Railroad and adjacent to the electrical substation.
Anticipated work activities for the coming week:
  • Cross 68th Avenue and continue force main installation along Railroad corridor.
  • Prepare for first pressure test of force main.