Work completed/in progress:
- No work Mon-Wed due to the winter storm.
- Preparing work site for pipeline installation following winter storm. Continuing HDPE pipe fusion.
Anticipated work activities for the coming week:
- Continue force main installation north of Sullivan Rd on MCRRC property.
- Second pipe crew on-site to begin force main installation south of Apple Avenue on MCRRC property.