Work completed/in progress:
- The final wall section was poured this week. The base slab and walls are now complete.
- Grand River is stripping forms from the previous wall section today.
Anticipated work activities for the coming week:
- Grand River will continue removing formwork and preparing for installation of the wall pipes and leak testing of the structure.