This was another good week of progress even with the round of snow.

 

Work Completed this Week (January 25 – 29)

  • Concrete banding of the Scallops were continued along with filling in of the scallops with decorative concrete.
  • The curb on the All Occasions Stairway was installed.
  • Site electrical and drainage work continued in various locations of the site including piping to connect the trench drains to the collection system.
  • Interior CMU walls were completed in the new restroom building.
  • Permanent power was installed at the new restroom building!

 

Anticipated Work Next Week (Weather Dependent)

  • Installation of the scallop ribbons will continue.
  • Colored concrete infill of the scallops will continue.
  • Site electrical and building electrical will be ongoing throughout the week.
  • Various site improvement features will be completed such as the Christmas tree stand and future kiosk foundation as well as various seat walls.